Hi All,
We are building a new home in Victoria and are about to execute a standard HIA building contract with the builder. There are a few items that I am unsure about. Was wondering anyone with experience on this can advise if this is within the accepted norms or should I negotiate these items.
Standard HIA contract, Page 6, Item 1.
Time For Completion : 270 days
Estimated delays :
– Incremental weather : 40 days
– Weekend, public holidays etc : 40 days
– Other days : 15 days
Are the above time frames normal ?
HIA contract Page 8 :
– Item 8 : Agreed interest for late progress payment : $20% Per annum
– Item 9 : Damages for delays : $150 per week
– Item 12 :Agreed damages for delays : $150 per week
What about late payment fee of 20%, this seems way above the standard lending rates considering that they only want to pay $150 per week for delays.
At the end of the contract, the builder has included a couple of sheets titled “Specification”. One of them says :
PRELIMINARY SITE WORKS
– Clearing of site by Owner or A Contract Variation
– Excavation of rock by Owner or a Contract Variation
Again is the above normal considering that they have already done a site inspection and costed for site costs of about $10,000.
TIA
Greg