I managed to fidd out some more details …
"In limited circumstances the Commissioner may approve an extension to the commencement and completion date where the delay was outside the control of the parties and could not have been foreseen at the time of entering into the contract."
"A letter from the relevant third party (e.g.: builder, developer, local council or private surveyor etc.) that clearly states the nature of the delays and the actual or anticipated dates foundations were/or are to be laid."
I was an owner builder, and the reason why the construction took longer than 18 months was due to delays with material supplies. As well as a couple tradies leaving half way through an unfinished job. Are these reasons acceptable? Do I need the supplier and tradies to write up letters, or is it just my statement (as an owner builder) that is required?