It all comes down to the brief given to the soil tester, the number of samples, where they have been taken from on the site etc. If the site previously had a building which had been razed and the rubble buried on site the results will vary widely. Soil testing must be undertaken in the area where the works are to be done, to a sufficient depth to give a soil profile which can then be interpreted by the engineer. The engineer should brief the soil tech appropriately and have some idea of the pre-existing soil conditions.
I have seen a few sites where the testing was inconclusive (and included in the tender documentation), it just led the PM to variation heaven – new pier/footing design, rubble removal, floaters etc.
90% of construction problems begin in the ground by having incomplete/non-reliable information about the ground conditions. Everything else above the ground can be controlled.