I am doing a sub-development of two homes in Adelaide. I recently recieved an amended copy of my plans from the builder that mysteriously included 2 1100 litre rainwater detention tanks on the side of each house. When I questioned why this was not on the plans I agreed to at contract the builder advised that they had been added by the engineers after contract signature in accordance with council requirements. Of course there is a clause in the contract that states stormwater management is my responsibility.
I have checked the council development plan and way down on page 27 or 373 it says
"Development which results in a total two dimensional roof area greater than 30 percent of the site area, should include on-site stormwater detention structures/techniques which control the discharge of stormwater from the site so that it does not exceed the rate of stormwater discharged by development with a 30 percent site coverage"
In other words, according to the council, I do need these tanks. However, as it is my responsibility to install stormwater management sometime after I accept the house from the builder, how will the council determine if they have been installed or not? Has anyone else encountered this problem?